Pennsylvania HB 2429: An Act amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in restructuring of electric utility industry, providing for hosting capacity maps.
Status: Referred to Consumer Protection & Professional Licensure (as of 2026-06-18)
State: Pennsylvania · Session: 2025-2026 · Bill: HB 2429
Sponsors: Melissa Cerrato, Elizabeth Fiedler, Liz Hanbidge, Nikki Rivera, Steven Malagari, Arvind Venkat, Mandy Steele, Danielle Friel Otten, Carol Hill-Evans, Johanny Cepeda-Freytiz, Lisa Borowski, Kyle Donahue, Heather Boyd, Ben Waxman, Tarik Khan, Joe Webster
Bill Text
PRIOR PRINTER'S NOS. 3230, 3370 PRINTER'S NO. 3575 THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL No. 2429 Session of 2026 INTRODUCED BY CERRATO, FIEDLER, HANBIDGE, RIVERA, MALAGARI, VENKAT, STEELE, OTTEN, HILL-EVANS, CEPEDA-FREYTIZ, BOROWSKI, DONAHUE, BOYD, WAXMAN AND KHAN, APRIL 20, 2026 AS AMENDED ON SECOND CONSIDERATION, HOUSE OF REPRESENTATIVES, JUNE 9, 2026 AN ACT Amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in restructuring of electric utility industry, providing for hosting capacity maps. The General Assembly of the Commonwealth of Pennsylvania hereby enacts as follows: Section 1. Title 66 of the Pennsylvania Consolidated Statutes is amended by adding a section to read: § 2807.1. Hosting capacity maps. (a) Duties of electric distribution companies.-- (1) By July 1, 2027, each electric distribution company shall develop and make publicly available distribution system hosting capacity maps on the electric distribution company's publicly accessible Internet website for respective service territories, which shall be updated every two months and prioritize feeders or nodes that experienced significant changes since the electric distribution company's previous update. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 (2) The commission may require each electric distribution company to include additional data points to improve transparency and planning, as necessary. (3) An electric distribution company may SHALL establish an online portal or registration process that enables a person to verify the person's identity to receive access to the hosting capacity maps on the electric distribution company's publicly accessible Internet website. AUTHORIZES AN ELIGIBLE PERSON TO ACCESS THE HOSTING CAPACITY MAPS UPON VERIFICATION THAT THE ELIGIBLE PERSON IS ENGAGED IN A PROJECT OR OTHER LEGITIMATE BUSINESS PURPOSE RELATED TO THE DISTRIBUTION NETWORK. (4) The commission shall ensure that an electric distribution company does not discriminate against, hinder or deny a AN ELIGIBLE person that properly requests access to the electric distribution company's distribution system hosting capacity maps. A AN ELIGIBLE person may file a complaint with the commission if the person believes the electric distribution company has denied or prevented access to an electric distribution company's hosting capacity map in violation of this section. (b) Hosting capacity websites.--The commission shall publish a list of hyperlinks for each electric distribution company hosting capacity map website on the commission's publicly accessible Internet website. (c) Standards.--The commission shall establish uniform reporting standards for consistency across each electric distribution company within nine months of the effective date of this subsection, subject to a stakeholder proceeding. At a minimum, standards shall address data format, methodology for 20260HB2429PN3575 - 2 - <-- <-- <-- <-- <-- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 calculating load hosting capacity, threshold criteria for constraint disclosure and map user interface requirements. (d) Preapplication period.-- (1) Within 30 days of the effective date of this subsection, each electric distribution company shall develop a preapplication report that provides general locational information to a person that proposes to interconnect new load or generation to the distribution system upon request, which shall include the proximity to distribution lines operating at a nominal voltage of at least 4 kV, existing interconnected generation and load, distribution system capacity and constraints relevant to interconnection viability and any other relevant information identified by the commission. (2) An electric distribution company shall provide the locational information to the person that proposes to interconnect to the distribution system within seven business days after a request is submitted to the electric distribution company. (e) Requirements.--The hosting capacity maps under subsection (a) shall include, at a minimum, the following: (1) Total available distribution system hosting capacity, expressed in kilowatts, for new loads. (2) A unified interface which shall identify the following: (i) A single unified interface with filtering or toggling mechanisms designed to identify the following: (A) Available hosting capacity for new load interconnections . (B) Available capacity for distributed energy 20260HB2429PN3575 - 3 - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 resource interconnection. (C) A distribution system constraint or characteristic identified by the commission as relevant to siting decisions for new large loads or generation. (ii) Existing and queued distributed energy resources. (iii) Distribution system constraints. (3) Display of circuit hosting capacity at circuit-level granularity, including feeder subsections. (4) Forecasts of approved system upgrades. (5)
View Pennsylvania HB 2429 on LegisTrack → — full text, sponsors, votes, campaign finance, and cross-state matches.