Massachusetts H 3533: An Act for field safety in gas infrastructure
Status: Accompanied a study order, see H5323 (as of 2026-04-06)
State: Massachusetts · Session: 194th · Bill: H 3533
Sponsors: Frank A. Moran
Bill Text
1 of 1 HOUSE DOCKET, NO. 1900 FILED ON: 1/15/2025 HOUSE . . . . . . . . . . . . . . . No. 3533 The Commonwealth of Massachusetts _________________ PRESENTED BY: Frank A. Moran _________________ To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General Court assembled: The undersigned legislators and/or citizens respectfully petition for the adoption of the accompanying bill: An Act for field safety in gas infrastructure. _______________ PETITION OF: NAME: DISTRICT/ADDRESS: DATE ADDED: Frank A. Moran 17th Essex 1/15/2025 1 of 10 HOUSE DOCKET, NO. 1900 FILED ON: 1/15/2025 HOUSE . . . . . . . . . . . . . . . No. 3533 By Representative Moran of Lawrence, a petition (accompanied by bill, House, No. 3533) of Frank A. Moran for legislation to provide for field safety in gas infrastructure by requiring that the Department of Public Utilities promulgate regulations establishing requirements for the maintenance, timely updating, accuracy, and security of gas LDC maps and records. Telecommunications, Utilities and Energy. The Commonwealth of Massachusetts _______________ In the One Hundred and Ninety-Fourth General Court (2025-2026) _______________ An Act for field safety in gas infrastructure. Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows: 1 SECTION 1. Chapter 164 of the General Laws is hereby amended by striking section 2 144, as appearing in the 2016 Official Edition, and inserting in its place the following: 3 Section 144. (a) There shall be uniform natural gas leaks classification for all gas 4 companies. 5 (b)(1) Gas companies shall assess a grade to all reported natural gas leaks based on the 6 system provided in this section. 7 (2) A Grade 1 leak shall be a leak that represents an existing or probable hazard to 8 persons or property. Grade 1 leaks require repair as immediately as possible and continuous 9 action until the conditions are no longer hazardous. The gas company shall immediately schedule 10 a completion of repairs and the condition shall be kept under continuous surveillance until the 2 of 10 11 hazard or source of the leak is eliminated. Whenever appropriate and feasible, a gas company 12 shall notify the fire department and chief law enforcement officer in each city or town where a 13 Grade 1 leak is identified. 14 (3) A Grade 2 leak shall be a leak that is recognized as non-hazardous to persons or 15 property at the time of detection, but justifies scheduled repair based on probable future hazard. 16 The gas company shall repair Grade 2 leaks or replace the main within 6 months from the date 17 the leak was classified; provided, however, that said repair or replacement may take place later 18 than six months from the date the leak is classified, but no later than 12 months from the date the 19 leak is classified, if any required permits for such repair or replacement are temporarily withheld 20 consistent with a seasonal moratorium. All Grade 2 leaks shall be reevaluated by a gas company 21 at least once every 6 months until eliminated; provided, however, that the frequency of 22 reevaluation shall be determined by the location and magnitude of the leakage condition. 23 (4) A Grade 3 leak shall be a leak that is recognized as non-hazardous to persons or 24 property at the time of detection and can be reasonably expected to remain non-hazardous. The 25 gas company shall reevaluate Grade 3 leaks during the next scheduled survey, or within 12 26 months from the date last evaluated, whichever occurs first, until the leak is eliminated or the 27 main is replaced. A municipal or state public safety official may request a reevaluation of a 28 Grade 3 leak prior to the next scheduled survey, or sooner than 12 months of the date last 29 evaluated, if the official reasonably believes that the Grade 3 leak poses a threat to public safety. 30 (c)(1) Upon the undertaking of a significant project on a public way exposing confirmed 31 natural gas infrastructure, and with sufficient notice, a municipality or the commonwealth shall 32 submit written notification of the project to a gas company. The gas company shall survey the 3 of 10 33 project area for the presence of Grade 1 or Grade 2 leaks and set repair and replacement 34 schedules for all known or newly detected Grade 1 or Grade 2 leaks. The gas company shall 35 ensure that any shut off valve in the significant project area has a gate box installed upon it or a 36 reasonable alternative that would otherwise ensure continued public safety and that any critical 37 valve that has not been inspected and tested within the past 12 months is verified to be 38 operational and accessible. The gas company shall provide the repair and replacement schedule 39 of gas leaks to the municipality or the commonwealth. 40 (2) Upon the undertaking of any planned project involving excavation for purposes of 41 performing maintenance on or co
View Massachusetts H 3533 on LegisTrack → — full text, sponsors, votes, campaign finance, and cross-state matches.