Oregon HB 3681: Relating to energy facilities.
Status: Chapter 305, (2025 Laws): Effective date January 1, 2026. (as of 2025-06-24)
State: Oregon · Session: 2025R1 · Bill: HB 3681
Sponsors: Mark Gamba, Janeen Sollman, Jeff Golden, Ken Helm, Tom Andersen
Bill Text
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 HB 3681-5 (LC 2730) 4/4/25 (CPA/ps) Requested by Representative GAMBA PROPOSED AMENDMENTS TO HOUSE BILL 3681 On page 1 of the printed bill, line 2, after “ORS” delete “215.213, 215.283,”. On page 2, line 15, after “shall” insert “make every effort to”. On page 3, line 23, after the period insert “The earliest date that the council may require construction of a facility to begin is six years from the date the council issues the site certificate.”. Delete lines 37 through 45 and delete pages 4 and 5. On page 6, delete lines 1 through 17 and insert: “SECTION 2. ORS 469.403 is amended to read: “469.403. (1) The Energy Facility Siting Council shall include in all of the council’s final orders approving or rejecting an application for a site certificate or amended site certificate any decisions related to or arising from a contested case on the application. Any party or lim- ited party to a contested case proceeding may apply for rehearing within 30 days from the date the approval or rejection is served. The date of service shall be the date on which the [Energy Facility Siting] council delivered or mailed its approval or rejection in accordance with ORS 183.470. The appli- cation for rehearing shall set forth specifically the ground upon which the application is based. No objection to the council’s approval or rejection of an application for a site certificate or a site certificate amendment shall be considered on rehearing without good cause shown unless the basis for the 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 objection is urged with reasonable specificity before the council in the site certificate or amended site certificate process. Upon such application, the council shall have the power to grant or deny rehearing or to abrogate or modify its order without further hearing. Unless the council acts upon the application for rehearing within 30 days after the application is filed, the application shall be considered denied. The filing of an application for re- hearing shall not, unless specifically ordered by the council, operate as a stay of the site certificate or amended site certificate for the facility. “(2) Any party or limited party to a contested case proceeding on a site certificate or amended site certificate application may appeal a final order issued by the council under ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992, including the council’s approval or rejection of the site certificate or amended site certificate application. Issues on appeal shall be limited to those raised by the parties or limited parties to the contested case proceeding before the council. To appeal a final order, a petitioner shall establish individual or associational standing by demonstrating an injury to the petitioner or petitioner’s members resulting from the final order. “(3) Notwithstanding ORS 183.482 and 183.484, jurisdiction for judicial review of the council’s approval or rejection of an application for a site certificate or amended site certificate, including decisions related to or arising from a contested case on an application for a site certificate or amended site certificate, is conferred upon the Supreme Court. Pro- ceedings for review shall be instituted by filing a petition in the Supreme Court. The petition shall be filed within 60 days after the date of service of the council’s final order approving or rejecting a site certificate or amended site certificate or within 30 days after the date the petition for rehearing is denied or deemed denied. Date of service shall be the date on which the council delivered or mailed its order in accordance with ORS 183.470. HB 3681-5 4/4/25 Proposed Amendments to HB 3681 Page 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 “(4) The filing of a petition for judicial review may not stay the order approving or rejecting a site certificate or amended site certificate, except that a party or limited party to the contested case, or any other person seeking judicial review of a decision related to or arising from a contested case, may apply to the Supreme Court for a stay upon a showing that there is a colorable claim of error and that: “(a) The petitioner will suffer irreparable injury; or “(b) Construction of the energy facility will result in irreparable harm to resources protected by applicable council standards or applicable agency or local government standards. “(5) If the Supreme Court grants a stay pursuant to subsection (4) of this section, the court: “(a) Shall require the petitioner requesting the stay to give an undertak- ing in the amount of $5,000. “(b) May grant a stay in whole or in part. “(c) May impose other reasonable conditions on the stay. “(6) Except as otherwise provided in ORS 469.320 and this section, the review by the Supreme Court shall be the same as the review by the Court of Appeals described in ORS 18
View Oregon HB 3681 on LegisTrack → — full text, sponsors, votes, campaign finance, and cross-state matches.