Missouri HB 2720: Modifies provisions related to land reclamation
Status: Public Hearing Completed (H) (as of 2024-04-10)
State: Missouri · Session: 2024 · Bill: HB 2720
Subjects: AGRICULTURE, CONSERVATION, DEPARTMENT OF, MINING AND OIL AND GAS PRODUCTION, NATURAL RESOURCES, DEPARTMENT OF
Sponsors: Lisa Thomas
Bill Text
SECOND REGULAR SESSION HOUSE BILL NO. 2720 102ND GENERAL ASSEMBLY INTRODUCED BY REPRESENTATIVE THOMAS. 5689H.01I DANA RADEMAN MILLER, Chief Clerk AN ACT Torepealsection444.766,RSMo,andtoenactinlieuthereofonenewsectionrelatingtoland reclamation. Be it enacted by the General Assembly of the state of Missouri, as follows: Section A. Section 444.766, RSMo, is repealed and one new section enacted in lieu 2 thereof, to be known as section 444.766, to read as follows: 444.766. 1. No provision of sections 444.760 to 444.790 shall apply to the 2 excavation of minerals or fill dirt for the purposes of construction or land improvement as 3 unrelated to the mining of minerals for a commercial purpose or reclamation of land 4 subsequent to the surface mining of minerals. 5 2. Nopermitisrequiredundersections444.760 to444.790 forthepurposeofmoving 6 minerals or fill dirt within the confines of real property where excavation occurs, or for 7 purposes of removing minerals or fill dirt from the real property as provided in this section. 8 (1) Excavations for construction pursuant to engineering plans and specifications 9 prepared by an architect, professional engineer, or landscape architect licensed pursuant to 10 chapter 327, or any excavation for construction performed under a written contract that 11 requires excavation of minerals or fill dirt, and the plans and specifications or written 12 contract establishes dates for completion of work and specifies the terms of payment for 13 work, shall be presumed to be for the purposes of construction and shall not require a permit 14 for surface mining. 15 (2) Excavations for purposes of land improvement where minerals removed from the 16 site are excess minerals that cannot be used on-site for any practical purpose [and at no time 17 are subjected to crushing, screening, or other means of beneficiation with the exception of EXPLANATION — Matter enclosed in bold-faced brackets [thus] in the above bill is not enacted and is intended to be omitted from the law. Matter in bold-face type in the above bill is proposed language. 18 removal of dead trees, decaying vegetation, tree limbs, and stumps] shall be presumed to be 19 for the purposes of land improvement and shall not require a permit for surface mining, 20 provided that: 21 [(a) ThesitehasnotbeendesignatedasasurfaceminebythefederalMineSafetyand 22 Health Administration; 23 (b)] (a) Minerals from the property are not used for commercial purposes on a 24 frequent or ongoing basis; and 25 [(c)] (b) A pit, peak, or ridge does not persist at the site as inconsistent with the 26 purposes of land improvement. 27 (3) Permitsshallnotberequiredfortheexcavationoffilldirt,regardlessofthesiteof 28 disposition or whether construction occurs at the site of excavation. 29 3. (1) If the director or his or her designee determines that a surface mining permit is 30 required for real property which is purported to be for purposes of construction or land 31 improvement not requiring a surface mining permit under this section, such determination 32 shall be sent in writing to the owner of the property by certified mail stating the reasons for 33 such determination. Upon request of the person receiving the letter, an informal conference 34 shall be scheduled with the director within fifteen calendar days to discuss the determination. 35 Following the informal conference, the director shall issue a written determination regarding 36 hisorherfindingsoffactnolaterthanthirtycalendardaysafterthedateoftheconference. If 37 the director agrees that a surface mining permit is required and the person disagrees with that 38 decision, the person may make a written request for a hearing before the commission at its 39 next regular meeting. Such written request shall be filed within thirty calendar days after 40 receipt of the director's written determination, except when the thirtieth day would be later 41 thanthedateofthenextregularlyscheduledcommissionmeeting,thewrittenrequestshallbe 42 filed at least seven days prior to the commission meeting unless the director and the person 43 filing the request mutually agree to place the matter on the commission's agenda for a later 44 meeting. The commission shall issue a written determination as to whether a surface mining 45 permit is required under this state's law within thirty calendar days after the hearing. The 46 written determination may be appealed as provided under this chapter. 47 (2) Until a final written determination has been issued under the process established 48 under subdivision (1) of this subsection, the person receiving a letter stating the reasons a 49 mining permit is required may continue activity at the site in dispute. The commission may 50 staythedirector'sdetermination. Ifthefinalwrittendeterminationisthatapermitisrequired, 51 all fees otherwise provided by statute or rules of the commission shall apply. If the 52 determination is that no permit is required, no permit fees shall be require
View Missouri HB 2720 on LegisTrack → — full text, sponsors, votes, campaign finance, and cross-state matches.